2.e) Award Bid #26-2615 for the renovation of the Wastewater Treatment Plant (WWTP) Breakroom Renovation Project to Pannonia Development, LLC, in the amount of $169,850.

  • Default_avatar
    Duane Wright at July 23, 2026 at 4:37am EDT

    Duane Wright
    6021 25th Ave N, Saint Petersburg / Italy & Romania
    This item should be table or rescinded, based on the information provided in the ITB [Intent To Bid] documents
    This project is not in compliance with the City’s Title II obligations.
    Namely the proposed design does not meet the requirements under Chapters: 2.3.4.6, and 8 as prescribed under the ADA Architectural guidelines.
    Because the Florida Building Code - Accessibility incorporated those guideline, this renovation as designed would violate those codes.
    There may be “loopholes” relying on the FBC-Existing Buildings and levels of alterations. Utilizing these “work arounds” to save face is disingenuous.
    Basically a total “gut-job.” It is in the best interest of the present and future employees, the tax-payers, and the City’s reputation be renovated in compliance from the start.
    Once there is a compliant ITB, it should be re-bid by all or the original bidders.